Re: '09 Kibbee Dome

From: Max Zaluska <flyezb_at_yahoo.com>
Date: Tue, 16 Dec 2008 09:21:47 -0000

Any plans for F1D Team Selection next year?

--- In Indoor_Construction_at_yahoogroups.com, "Chris Borland" <candjborland@...> wrote:
>
> Hi All,
>
> I just received a call from Andrew Tagliafico about the Kibbee Dome and he has asked
me to
> pass on bad tidings about the '09 meet. It was already known that the ends of the Dome
had
> to be (must be) replaced in the near future. Unfortunately, the near future is here!
Starting in
> March (after the snow is gone) both ends will be replaced and brought up to something
> resembling code before winter and more snow. For some reason 2 x 2's and plywood
sheet
> don't seem to be acceptable anymore.
>
> At this time Andrew doesn't know if the rest of the projected work will be done at this
time.
> This work involves lowering the floor about 15' and adding an extra section of seats
where
> the running track now is for TV purposes. The ceiling would also be lowered the same
> amount and flattened off (great for us). The number I heard is around $50,000,000 for
the
> whole project so don't hold your breath. We will probably all be too old to fly when this
part
> happens.
>
> Anyway, no Kibbee Dome for '09 but '10 should be on.
>
> Chris Borland - Sacramento
>
Received on Tue Dec 16 2008 - 01:21:52 CET